| SAVICE SCHOOL BUILDING OPERATIONS 2009 -2010: MONITORING REPORT |
| Date of report: |
15-Jan-10 |
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
| Project Name/ Date completed |
Điện Bàn, Quảng Nam |
Lý Nhân, Hà Nam |
Ninh Ich, Ninh Hoa, Nha Trang |
Long Hồ, Vĩnh Long |
Cu Jut, Dak Nong |
Thuận Nghĩa
Quỳnh Lưu Nghệ An
|
Phú Xuyên, Hà Tây |
Pleichet, Gia Lai |
Hàm Thuận, Bình Thuận |
|
| Solicitated by/ Recommended/ Sponsored by |
Anh Vịnh, SAVICE USA |
chị Khánh Vân, USA |
anh Ba Long |
Soeur Phượng |
Savice Team |
Chú Thuyên |
Savice Team |
Savice Team |
Savice Team |
|
| 1. Project planning and cost setting |
1-May-09 |
15-Jun-09 |
1-Aug-09 |
Mar - Apr 09 |
Apr-09 |
Aug-09 |
Sep-09 |
Feb-10 |
Nov-09 |
|
| 2. Site visit, plan checking, cost review |
18-Jul-09 |
20-Jul-09 |
5-Dec-09 |
6-Apr-09 |
Sep-09 |
Dec-09 |
13-Mar-10 |
4-Apr-10 |
pending |
|
| 3. Write up Project Application |
12-Jun-09 |
15-Dec-09 |
pending |
31-Aug-09 |
Nov-09 |
Dec-09 |
30-Mar-10 |
30-Apr-10 |
pending |
|
| 4. Project Appraisal and Due diligence |
30-Jun-09 |
12-Mar-10 |
Reject |
pending |
Jan-10 |
15-Feb-10 |
30-Apr-10 |
|
|
|
| 5. Construction license and formalities done |
12-Aug-09 |
12-Mar-10 |
|
Reject |
pending |
12-Mar-10 |
|
|
|
|
| 6. Savice's Letter of Approval |
10-Sep-09 |
24-Mar-10 |
|
|
|
3-Apr-10 |
|
|
|
|
| 7. Contractor sign-up and construction start |
26-Dec-09 |
25-May-10 |
|
|
|
16-Apr-10 |
|
|
|
|
| 8. SAVICE's donation - first phase |
11-Sep-09 |
25-May-10 |
|
|
|
|
|
|
|
|
| 9. Construction progress - report/ supervision |
15-Jan-10 |
|
|
|
|
|
|
|
|
|
| 10. SAVICE's donation - following phases |
26-Jan-10 |
|
|
|
|
|
|
|
|
|
| 11. Construction completes, interior fittings |
25-Mar-10 |
|
|
|
|
|
|
|
|
|
| 12. SAVICE's donation - last phase |
28-Mar-10 |
|
|
|
|
|
|
|
|
|
| Inauguration, School open |
|
|
|
|
|
|
|
|
|
|
| Definition |
Colour Code |
| |
Project Description |
| |
Under solicitation, discussion process |
| |
The project is rejected by Savice team at its discretion. Letter of Refusal sent to relevant parties. |
| |
The project is postponed/ delayed by the sponsor due to license, or external reasons. |
| |
The planning date by Savice team to achieve/ monitor. |
| |
The project is completed and delivered to the school administrator. |